3rd Quarter 2011
- MILRA coordinates with on-site credit unions.
- Zoning blueprint and legislation is completed
- MILRA solicits a commercial broker
- MILRA /Broker issues solicitation for developer – solicitation package includes elements of a development agreement.
- MILRA and US Army continue to work on final development agreements
4th Quarter 2012
- MILRA works to assemble state and local investments in the EDC parcel and commitments to the establishment of the Launch Facility.
- Developer(s) are selected for redevelopment of the property.
- Consultant is selected for the Launch Facility.
- Private Development Agreements (if applicable) and Cooperative Agreements are executed.
1st Quarter 2012
- MILRA coordinates with Atlanta Development Authority and City of Atlanta on TAD authorization and requests for issuance of bonds.
- MILRA, City of Atlanta, Atlanta Development Authority and other agencies define and establish infrastructure projects for TAD funding.
- MILRA meets and coordinates with Congressional Delegation/Staff on alternative funding.
- MILRA increases staffing hiring a Development Director and Administrative Assistant.
- Launch Facility analysis and design begins.
2nd Quarter 2012
- Interim Leasing Continues
- MILRA, City of Atlanta, Atlanta Development Authority and other agencies define and establish infrastructure projects for TAD funding.
- MILRA assists in the coordination and execution of FOST or FOSET documents and completion of state environmental impact considerations.
- First phase properties are conveyed.