Projected Timeline

3rd Quarter 2011

  • MILRA coordinates with on-site credit unions.
  • Zoning blueprint and legislation is completed
  • MILRA solicits a commercial broker
  • MILRA /Broker issues solicitation for developer – solicitation package includes elements of a development agreement.
  • MILRA and US Army continue to work on final development agreements

4th Quarter 2012

  • MILRA works to assemble state and local investments in the EDC parcel and commitments to the establishment of the Launch Facility.
  • Developer(s) are selected for redevelopment of the property.
  • Consultant is selected for the Launch Facility.
  • Private Development Agreements (if applicable) and Cooperative Agreements are executed.

1st Quarter 2012

  • MILRA coordinates with Atlanta Development Authority and City of Atlanta on TAD authorization and requests for issuance of bonds.
  • MILRA, City of Atlanta, Atlanta Development Authority and other agencies define and establish infrastructure projects for TAD funding.
  • MILRA meets and coordinates with Congressional Delegation/Staff on alternative funding.
  • MILRA increases staffing hiring a Development Director and Administrative Assistant.
  • Launch Facility analysis and design begins.

2nd Quarter 2012

  • Interim Leasing Continues
  • MILRA, City of Atlanta, Atlanta Development Authority and other agencies define and establish infrastructure projects for TAD funding.
  • MILRA assists in the coordination and execution of FOST or FOSET documents and completion of state environmental impact considerations.
  • First phase properties are conveyed.